The check job's macOS leg has little headroom before its 50-minute warning: across nine merge-group runs on 2026-10-18 it took 35.2, 36.5, 38.9, 42.3, 42.4, 43.0, 43.9, 49.4 and 44.8 minutes, and the run of #1099 came within 0.6 minutes of the warning. Nearly all of it is the one race-enabled pass over the whole module, 41.9 to 47.4 minutes in the last three; the plain-only guard step after it takes under a minute. The warning fires at 50 and the job ceiling is 60.
issueresolvedminoriss-2610181711260494
The check job's macOS leg has little headroom before its 50-minute warning: across nine merge-group runs on 2026-10-18 it took 35.2, 36.5, 38.9, 42.3, 42.4, 43.0, 43.9, 49.4 and 44.8 minutes, and the run of #1099 came within 0.6 minutes of the warning. Nearly all of it is the one race-enabled pass over the whole module, 41.9 to 47.4 minutes in the last three; the plain-only guard step after it takes under a minute. The warning fires at 50 and the job ceiling is 60.
Grounds
- pursued: a merge-group macOS leg stays below 60 minutes, so the warning fires only on a run slower than any seen; one past 60 would show the leg needs a faster pass, not another raise
Frontmatter
| id | iss-2610181711260494 |
|---|---|
| type | issue |
| lifecycle | resolved |
| severity | minor |
.abcd/work/issues/resolved/iss-2610181711260494-the-check-job-s-macos-leg-has-little.md
open on GitHub ↗ · commit history ↗
mentions4
- dcn-26101817563282492026-10-18 — The check job's macOS leg takes a 70-minute ceiling, with its warning at 60, raised from 60 and 50 by the coordinating session on delegation from the technical facilitator, who is away until 2026-10-23 (iss-2610181711260494). Across ten merge-group runs on 2026-10-18 the leg took 35.1 to 49.3 minutes, and one came within 0.7 minutes of its 50-minute warning. Its one race-enabled pass keeps a steady 2.80 to 2.85 of the runner's three test slots busy, so the leg is set by its total work rather than by one package: the slowest, internal/core/implement/loop, starts 8 to 12 minutes in and ends 2.5 to 4.2 minutes before the pass does. Its time varies with the runner, since the same tree's package times summed to between 5,738 and 8,050 seconds. The new ceiling stays under the merge queue's 90-minute check response timeout, and the warning keeps its 10-minute lead. The per-package -timeout stays at 40 minutes: the slowest package under race took at most 1,901 seconds, 31.7 minutes, a margin of 8.3. release.yml's verify job is not touched, since it runs the ubuntu race lane, about 21 minutes, under its 55-minute ceiling, not this pass. Starting the loop package first was not taken (at most 2 to 3 minutes, against a list pinned in three files), nor was running it without the race detector on macOS (the macOS-only flakes seen so far came from the race leg). Cutting the pass's total work is the longer lever, captured on its own.
- dcn-26102820362195032026-10-28 — facilitator-on-delegation: the coordinating session (abcd-f5), on delegation from the technical facilitator, raises the check job's macOS leg ceiling in ci.yml from 70 to 85 minutes and moves its warning line from 60 to 75, keeping it ten minutes ahead; the ubuntu leg stays at 45. On 2026-10-28 merge-group run 40752008734 (PR #1196) had check (macos-latest) cancelled after about 71 minutes, from 19:11:30Z to 20:22:05Z, and the queue dropped the group with failed_checks, while that day's passing merge-group runs took roughly 46 to 68 minutes. 85 stays below the merge queue's 90-minute check response timeout. The lasting remedy is still a faster suite: iss-2610181711260494 named it and was resolved by the raise to 70, and the faster race pass stays open as iss-2610181757540736; this resolves iss-2610282035340363.
- iss-2610180545134593The implement loop package's tests are bound by git subprocesses: the slowest, TestPollingWithoutAnAnswerNeverHoldsTheIssuePastOneLease, runs Drain 120 times (a 4-minute poll over four 2-hour leases, kept inside the 5-minute take-over margin on purpose) and took 67s plain on a loaded machine, 31s on a quieter one with 3.84s of its own CPU; the next three take about 20s each, and the package is the slowest in both of the ubuntu leg's passes (320-410s plain, 470-650s race on 2026-10-18), with none of its 500 tests parallel.
- iss-2610282035340363The macOS leg of the check job in ci.yml cancels merge-group runs at its 70-minute ceiling: on 2026-10-28 run 40752008734 (PR #1196's merge group) had check (macos-latest) cancelled after about 71 minutes, from 19:11:30Z to 20:22:05Z, and the queue dropped the group with failed_checks. That day's passing merge-group runs took roughly 46 to 68 minutes, so the leg runs near its cap and each cancel rebuilds every group queued behind it. The lasting remedy is a faster suite (iss-2610181711260494, resolved by the raise to 70, which named a faster race pass, iss-2610181757540736, as the longer lever).